44th Avenue East roadway projects underway
U.S. 41 to 19th Street Court East -- Completed and open to traffic.
19th Street Court East to 30th Street East -- Construction ongoing.
Specific activites include:
Excavate ponds and place fill from 19th Street Court East to 30th Street East
Clearing and grubbing along the west side of 30th Street East
De-mucking existing pond near 19th Street Court East
30th Street East to 45th Street East -- Construction ongoing.
Specific activites include:
Complete installation of curb, base and sidewalks from 34th Street East to 37th Street East
First lift of asphalt from 30th Street East to 37th Street East
Pond East 2 liner installation
36'' water main installation
Placing fill and stabilizer between 39th Street East and 45th Street East
45th Street East to 44th Avenue Plaza East -- Design ongoing. Thirty percent of design submittal has been received and is under review
44th Avenue Plaza East to Lakewood Ranch Boulevard --Design ongoing
This story was originally published April 18, 2016 at 5:08 PM with the headline "44th Avenue East roadway projects underway ."