New locks for Panama Canal near half-way point

Miami HeraldApril 8, 2013 

GATUN, Panama -- The Panama Canal's expansion is finally beginning to look like a channel that will float some of the biggest ships in the world by mid-2015.

About 42 percent of the work on the new locks has been completed and it's by far the most costly and complicated part of the $5.25 billion project to retrofit the nearly century-old canal with larger locks to lift and lower ships on both the Atlantic and Pacific sides of the isthmus. The old locks will still be in service but the new ones will allow the canal to handle so-called post-Panamax ships, which are too big to fit through the existing locks.

Most of the rest of the canal renovation, such as deepening and widening channels along the original route of the canal and construction of new access channels, is finished or nearly so. In early March, a milestone was reached when dredging of Culebra Cut, the narrowest part of the canal that straddles the Continental Divide, was completed.

But for Panama, which gets about $1 billion a year from the canal, the project needed to be done yesterday.

Maersk Line, the world's largest container shipping line, has stopped using the

Panama Canal for its Asia service to U.S. East Coast ports. Next week, it plans to resume Asian sailings to the Eastern Seaboard through the Suez Canal.

Because the Suez can accommodate post-Panamax vessels, Maersk officials say it's more cost-effective. Maersk has not said whether it will run its Asia service through the Panama Canal once the expansion is completed.

Jorge Quijano, chief executive of the Panama Canal Authority, said he expects the new locks will help Panama bring "back home" some of the services that have switched to the Suez.

Work on the expansion is about eight months behind schedule, mainly because the international consortium working on the locks didn't initially get the concrete mix right. "We wanted a mix that could be guaranteed for the next 100 years," said Jorge de la Guardia, executive director of the PCA's locks project management division. Heavy rain and a few strikes also have set the work back.

But a new canal visitor's center overlooking the Atlantic construction site and Gatun Lake opened right on schedule -- Aug. 15, 2012, the 98th anniversary of the opening of the canal.

Long before anyone dreamed of a canal, this narrow isthmus in Panama was known as the "golden route" and was the pathway over which much of the gold from the New World was sent to Spain. Later, during the California gold rush, miners crossed the isthmus to board ships heading up to California.

Now the gold comes from ship crossings. A container ship pays as much as $400,000 to traverse the canal. On a recent day eight ships were stacked up in Gatun Lake ready to enter the Atlantic locks as workers poured concrete at the excavation site.

Fees for using the new locks are still being worked out but it's crucial that the canal authority get them right so the canal will be able to compete with U.S. West Coast ports and the Suez Canal -- and to ensure that shipping lines will continue to send smaller ships through the original locks.

Construction on the Atlantic side of the canal near the city of Colon is proceeding quicker than on the Pacific where the capital Panama City sits. But that's because an old site where the Americans began work on a canal expansion in 1939 could be used.

That expansion was strategic. The United States, which controlled the 50-mile long canal until 1999, wanted to be able to move battleships between the Atlantic and Pacific and the ships were too large to make it through the locks.

But the project was abandoned in 1942 after the Pearl Harbor attack as the United States devoted its full attention to the war. After the war, the U.S. had both Atlantic and Pacific fleets and never revived its plans for the larger locks.

The excavation sites became water-filled ditches full of fat alligators, big fish and even abandoned cars, said de la Guardia.

But on the Atlantic side, the old ditch and the site chosen for the new locks and access channel overlapped almost perfectly, giving engineers a head-start. On the Pacific side, the canal authority didn't like the site excavated by the Americans and are constructing the new locks nearby on a site with a more solid basalt rock foundation.

That means the Atlantic side of the expansion could be finished by the end of 2014 or the beginning of 2015, allowing testing of the new locks and training to begin while work proceeds on the Pacific side, said de la Guardia.

Bradenton Herald is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.